    Governor briefed by PWD officials on status of works regarding National Highways and PMGSY pojects

    Publish Date: April 5, 2023
    PWD Officials

    Aizawl, the 5th April 2023: Governor Dr. Haribabu Kambhampati was briefed by Engineer-in-Chief PWD Pu C. Lalchhuana and his senior colleagues regarding the status or various works under National Highways and PMGSY projects. PWD officials made presentations on status of National Highway projects and PMGSY projects separately.

    The Governor remarked that he wanted to discuss the progress of different projects, reasons for delays in project timelines, constraints and issues which arise in taking projects forward. He asked the officials to apprise him of issues which need to be taken up with Ministry of Road Transport and Highways in this regard. Speaking about the BG Railway line from Bairabi to Sairang, he said four railway stations along this line need to be connected to the nearest villages/habitations and asked PWD officials to send DPRs on these to either MDoNER or NEC.

    According to the presentation, Mizoram has a total length of 1509 kilometres of National Highways, out of which 650 kilometres are under the PWD and the rest under NHIDCL. At present, PWD is 6 major on-going works to the tune of Rs. 2554.98 crores. Some of these are – NH-108(Sairang – New Eden, Tripura) which is 94 percent completed; NH-501A(Lawngtlai – Zochachhuah, KMTTP) which is 98.01 precent completed and under NH-2 (Seiling-Tuivai), a stretch of 17.5 kilometres has been completed recently. 3 new projects to the tune of Rs. 97.48 crores has been sanctioned and a further 6 proposals have been sent to MORTH for funding. Among the new proposals, PWD officials apprised the Governor about the importance of construction of a permanent bridge over river Tuivai on NH-2, which at present has no bridge and is a vital link connecting Mizoram and Manipur.

    Under Pradhan Mantri Gram Sadak Yojana (PMGSY) from the year 2000, under 12 Phases, 351 projects covering a road length of 4482.732 kilometres worth Rs. 2840.08 crores have been sanctioned providing connectivity to 232 habitations. 300 projects have been completed so far with another 51 projects under various stages of completion which have connected 216 habitations so far; 16 habitations are yet to be connected, work is in progress.

     

    PWD in Larsap hnenah National Highway leh PMGSY chungchangah presentation nei (Mizo)

    Aizawl, the 5th April 2023: Vawiin khan Raj Bhawan Conference Room ah PWD hotuten Governor Dr. Haribabu Kambhampati hnenah an Department hnathawh leh hmalakna thenkhat – National Highway leh Pradhan Mantri Gram Sadak Yojana (PMGSY) chungchang presentation siamin an hrilhfiah.

    Larsap chuan PWD hotute a koh chhan sawiin hna hrang hrang in kalpui mek dinhmun te, hna a hun taka zawhloh a nih chhan te leh hemi kawnga harsatna in nei te hriat ka duh a, hengte hi Ministry lamah keipawhin sawipui leh thlen ka duh vang a ni, a ti.

    PWD hotute tarlan danin PWD in National Highway leh a kaihhnawih hna 5 cheng vaibelchhe 2554.98 hu an thawk mek a; heng zinga NH-108(Sairang – New Eden, Tripura) chu za zelah 94 zawh a ni tawh a ; NH-501A(Lawngtlai – Zochachhuah, KMTTP) chu za zelah 98.01 zawh tawh niin NH-2 (Seiling-Tuivai) in a huam chhunga, km 17.5 a thui chu tunhnai khan zawh fel a ni a; hna dang 2 te chu thawh mek a nib awk. Heng bakah hian National Highway hna thar 3 tan tur an nei a, hna dang 6 pawh proposal Ministry of Road Transport and Highways (MORTH) an an thehlut mek a ni. Hemi zinga Tuivai lui chunga leidawh tur chu a pawimawh em avangin hemi chungchang chu a hranpa in Larsap in Ministry lam a sawipui tur thu PWD hotute a hrilh a ni.

    Pradhan Mantri Gram Sadak Yojana (PMGSY) hnuai hmalakna te chu PWD hotuten an tarlang leh a. PMGSY hi kum 2000 atanga thawh tan niin Phase 12 hnuaia Mizoram pumah project 351, kawng kilometre 4482.732 a thui cheng vaibelchhe 2840.08 man sanctioned a ni a. Heng zinga project 300 chu thawh zawh tawh niin project 51 thawh mek a ni a, sanctioned kilometre 4482.732 atangin 4247.534 a thui chu zawh tawh niin kilometre 277.735 hi an la thawk mek a. Heng project katlang hian khua 232 zinga 216 chu PMGSY kawng a nei tawh a ni. Larsap chuan Bairabi leh Sairang rel kawng inkara Railway Station 4 awm te chu a bulhnaia khua awmte nen inkawlpawhna sial a pawimawh thusawiin hemi chungchanga hmalak pawimawh a tih thu a sawi.

    Mizoram chhungah National Highway sial tawh leh sial mek zawng zawng thui zawng chu kilometre 1509 a ni a, hemi zinga kilometre 650 chu PWD in a sial tawh leh hma an lak mekte a ni a; a bak chu NHIDCL in chan te an ni. Heng zinga thui ber chu tunah NH-2 tia vuah tak – Seling – Tuipang (NH-54) leh Seling Tuivai(NH-150) suihfin, kilometre 481 a thui hi a ni.

     

    Written by: Pratap Chhetri, MIS, Deputy Director