    Governor reviews the works progress of NHIDCL in Mizoram

    Publish Date: March 6, 2023
    NHIDCL

    Aizawl, the 6th March 2023: NHIDCL officials led by Shri Virender Jokhar, Executive Director met Governor Hari Babu Kambhampati at the Raj Bhavan today. The NHIDCL officials apprised the Governor of the progress in their ongoing projects and also discussed with him some issues that needed to be resolved.

    Apart from the 4-lane road construction project which is put on hold due to dispute, Governor Hari Babu Kambhampati was pleased to learn that 60% of physical works in the ongoing road infrastructural projects taken up by NHIDCL is now achieved. He urged the NHIDCL to try their best efforts to find solutions to each problem that might crop up to complete their projects by March 2024 as stipulated. He also reiterated the importance of the 2-lane, and 4-lane road construction and railways project and the impact it will have in state economy.

    Out of the total length of the National Highway in the state, the NHIDCL is entrusted to construct 888 kilometres of road in the state. Out of the total length entrusted to them, 248 km is completed, ongoing works cover 560 km and 80 km is yet to be taken up.

    As per the overview of the project reported, NHIDCL is the executing agency for JICA funded NE Road Network Connectivity improvement project Phase -1: Aizawl to Tuipang, Phase -2: 4 numbers of Bypasses on Aizawl to Tuipang and MoRT&H funded Bharatmala Pariyojana: Seling -Champhai, Lunglei -Tlabung, Tuivai -Keifang and Vairengte – Sairang – a total length of 732.10 Km with the project cost of Rs 14944.94 crores. NHIDCL will also be taking up construction of a 4-lane road : Aizawl – Vairengte and 2-lane road : Keifang -Tuivai road package -II, a total length of 103.11 km with a project cost of Rs 1389 Crores.

    Governor hovin NHIDCL kawngpui siam meka hnathawh thlirho (Mizo)

    Aizawl, the 6th March 2023: Vawiin chawhma khan Governor Hari Babu Kambhampati chuan Virender Jokhar, Executive Director, NHIDCL leh a thawhpuite a kawm a. He hunah hian Mizoram hmun hrang hranga NHIDCL in project hrang hrang – kawngpui siam hna leh hna dang a thawh mek te thlirho a ni a. NHIDCL hotute chuan an hmasawnna bakah harsatna an neih mek hmanhmawh zawka a chinfel ngai te Governor hnenah hian an thlen a ni.

    Governor Hari Babu Kambhampati chuan Aizawl to Vairengte kawngpui 4-lane a zauh tur, la thawh theih rih loh mahse National Highway 2-lane a siam mek te 60% lai thawh zawh a ni ta chu lawmawm a tih thu a sawi a. NHIDCL te chuan an hnathawhnaah harsatna an neih te chu chinfel zung zung dan an dap thiam a ngai a, kum 2024 March thla a lo thlen chuan 2-lane NH kawngpui te hi hman theih tura Siam zawh hman a ngai a ni a ti. Mizoram tan kawngpui tha leh Rel kawng te hi a pawimawh tak zet a, heng hmasawnna ruhrel liantham leh pawimawh tak te hi siam zawh a nih hun chuan Mizoram economy hmelhmang nasa takin a danglam dawn tih a sawi bawk.

    Mizorama National Highway awm mekah hian NHIDCL hian enkawl/siam tur a nei thui ber a. Tunah hian National Highway siam tur an neih KM 888 a thuiah hian KM 248 an siam zo tawh a, KM 560 siam la hmabakin KM 80 a thui pawh siam belh an tum mek bawk a ni.

    NHIDCL official ten report an pek dan chuan JICA sum hmangin NE Road Network Connectivity improvement project Phase -1: Aizawl to Tuipang, Phase -2: 4 numbers of Bypasses on Aizawl to Tuipang leh MoRT&H sum hmangin Bharatmala Pariyojana hnuaiah Seling -Champhai, Lunglei -Tlabung, Tuivai -Keifang leh Vairengte – Sairang siam hna thawh mek a ni a. Heng project hnuaiah hian kawngpui 2-lane 732.10 Km a thui chu Rs Rs 14944.94 crores sengin siam mek a ni. NHIDCL chuan 4-lane road : Aizawl – Vairengte leh 2-lane road : Keifang -Tuivai road package -II te pawh an la thawk leh dawn e. Hemi hna thawhna tur China kawngpui thui zawng chu 103.11 km niin a siamna atan Rs 1389 Crores ruahman a ni.

     

    Written by: Malsawmsanga, MIS, PRO to Governor